Visualising the architecture is essential for technical alignment, but you also need to visualise the delivery of that architecture. This ensures stakeholders understand the timeline, dependencies, and current status.
Gantt charts are a powerful tool for showing the project’s timeline and the relationships between different tasks or workstreams.
gantt
title Example: Project Alpha Architecture & Delivery
dateFormat YYYY-MM-DD
section Discovery
System Context Design :done, des1, 2026-04-01, 2026-04-07
Requirement Gathering :done, des2, 2026-04-01, 2026-04-14
section Implementation
Container Architecture :active, imp1, 2026-04-15, 2026-05-01
API Development : imp2, 2026-04-20, 2026-06-15
Infrastructure Setup : imp3, 2026-05-01, 2026-05-20
section Validation
Security Audit : val1, 2026-06-01, 2026-06-15
UAT : val2, 2026-06-16, 2026-06-30
done, while “Container Architecture” is active. This gives an immediate visual cue of where the team is currently focused.